February 21, 2014

Sawmill construction imminent?

Underground utilities complete. Harris anticipates vertical construction to begin within 30 days.

Live Oak —

Klausner Lumber One LLC could soon begin construction on a sawmill that will be located at the catalyst site in Northwestern Suwannee County. Meanwhile, improvements continue on county owned land at the catalyst site.

The catalyst site is located Northwest of the I-10 and US 90 interchange. CenterState Bank in Jacksonville owns approximately 236 acres at the site, the county owns approximately 287 acres (25 acres not on catalyst site), and 120 acres was deeded to Klausner Lumber One LLC.

Klausner Lumber One

According to County Administrator Randy Harris, the general contractor for Klausner is on site and ready to begin construction immediately. To date, the company has installed underground utilities and is ready to begin vertical construction. Harris said he anticipates construction to begin on the site within the next 30 days.

169th Road

169th Road, a road that leads to the catalyst site from US 90, is currently under reconstruction, along with the access road that connects 169th Road to the Klausner site. Harris said the road is being reconstructed to handle the anticipated truck load. This project is being funded by the Florida Department of Transportation. 

US 90 turn lanes

Designs for turn lanes onto 169th Road from US 90 are currently underway. The designs include the extension of the four lanes that currently exist at the interchange of US 90 and I-10, and will extend west to accommodate the turn lanes onto 169th Road. Harris said he anticipates the designs being completed by September. Once the designs are completed, the project will go out to bid. Construction on the turn lanes could begin in mid-December. This project is also being funded by FDOT.

Water treatment plant

The county is currently in the bid process for the construction of the water treatment plant, which will be located on the Southwest side of the catalyst site. The deadline for all bids is today (Friday). Harris said construction of the water treatment plant is likely to begin within 30 days. Two test wells and two monitoring wells have been installed already. The project is being funded by the Community Development Block Grant.  

 

1
Text Only
Local News
Business Marquee
AP Video
Raw: Massive Dust Storm Covers Phoenix 12-hour Cease-fire in Gaza Fighting Begins Raw: Bolivian Dancers Attempt to Break Record Raw: Israel, Palestine Supporters Rally in US Raw: Palestinians and Israeli Soldiers Clash Raw: Air Algerie Flight 5017 Wreckage Virginia Governor Tours Tornado Aftermath Judge Faces Heat Over Offer to Help Migrant Kids Kerry: No Deal Yet on 7-Day Gaza Truce Kangaroo Goes Missing in Oklahoma More M17 Bodies Return, Sanctions on Russia Grow Gaza Residents Mourn Dead Amid Airstrikes Raw: Deadly Tornado Hits Virginia Campground Ohio State Marching Band Chief Fired After Probe Raw: Big Rig Stuck in Illinois Swamp Cumberbatch Brings 'Penguins' to Comic-Con Raw: Air Algerie Crash Site in Mali Power to Be Restored After Wash. Wildfire Crashed Air Algerie Plane Found in Mali Israel Mulls Ceasefire Amid Gaza Offensive
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
House Ads
Twitter Updates
Suwannee Democrat on Facebook
Poll

Did your student take advantage of local summer activities?

Yes, through 4-H or another club.
Yes, through Parks & Recreation.
Yes, summer food service program.
No, they didn’t.
No, we didn’t know there were any.
     View Results
Facebook